Background:

A steel fabrication plant in the East Rand approached us early 2016 to help them reduce their electricity costs.

This plant had a Power Factory Correction of 0,39. By installing a power factor correction system worth R235,000, we helped this customer reduce his maximum demand by 59%, which translated into a monthly reduction in electricity costs of R21,000 and an ROI of 10.3 months

ROI:
10,3 Months

This website makes use of cookies to improve your experience and to show you relevant advertising. By clicking “Allow All”, you agree to the storing of cookies on your device. Because we respect your right to privacy, you can choose not to allow some types of cookies. Click the “Manage Cookies” button to choose what you allow us to track.